EU Reaches Provisional Deal on Energy Project Permits
The European Parliament and the Council of the European Union reached a provisional deal on 18 November 2026 on a directive intended to speed up permits for renewable energy, electricity grids and energy storage across the EU, according to the Council. The agreement remains subject to endorsement and formal adoption.
The Council said the proposed changes cover both project approvals and grid connections for renewables, storage facilities and recharging stations. Procedures for authorising new gas and electricity infrastructure are also included, with the agreement providing for faster processing and greater transparency.
For applicants, the Council said the agreement provides for a shared online entry point to permitting procedures. This would take the form of either a single digital portal or linked portals at the appropriate level of administration.
According to the Council, national governments would also have the option of counting an authority’s non-response as approval at certain intermediate stages of permit administration. That option would not extend to the final decision on whether to grant a permit.
The Council said another provision would let member states apply a presumption of overriding public interest to renewable-energy deployment and electricity grids. Governments would retain the discretion to withhold that presumption where security, defence or cultural heritage interests require protection.
Citizen participation is addressed through principles that include the voluntary use of an independent facilitator, according to the Council. The deal also provides for fair sharing of benefits with communities hosting renewable-energy projects with more than 7 MW of installed capacity.
In its background account, the Council put the current completion time for electricity transmission grids at roughly 10 years, with permit procedures accounting for over half of that period. It said the European Commission submitted the directive proposal in December 2025 to address bottlenecks affecting renewable projects and energy infrastructure, covering gas and electricity grids, storage facilities and recharging stations.
According to the Council, both institutions must still endorse the agreement, and formal adoption requires legal-linguistic revision. Following adoption, member states would have an 18-month period to incorporate the directive into their national legislation.
* This article is based on publicly available information at the time of writing.